Schedule Acceleration Planning in Construction Project (Case Study: Japek II Selatan Tollroad)

Authors

  • Aziz Irsyad Telkom University, Indonesia
  • Ika Arum Puspita Telkom University, Indonesia
  • Wawan Tripiawan Telkom University, Indonesia

DOI:

https://doi.org/10.25124/ijies.v6i01.145

Keywords:

CPM; Planning; Overtime; Crashing; Scheduling

Abstract

This study focuses on the remaining work at stations (STA) 53+950 to 54+550 in Jakarta – Cikampek
II Selatan Toll Road Package III project to find the critical path, completion durations, and project
costs before and after acceleration. The CPM Technique was used to compile network planning
diagrams, determine the critical path and project duration. Crashing Project was applied to crash
schedule through the total project duration and cost whose changes due to the implementation of the
crashing method. The critical path was found in mobilization, tree felling, clearing, dig and haul,
borrow material, subgrade preparation, base course (A grade), subbase course (B grade), drainage
layer, lean concrete (t=10 cm), concrete pavement, concrete barrier type B, and signage. In the CPM,
the duration of project completion is 214 days. The total project budget under normal circumstances
is Rp22.073.412.654. After accelerating with the Crashing Project by proposed overtime was obtained
the reduced total cost of Rp32.004.882 from the total normal cost of Rp22.073.412.654 to
Rp22.041.407.771 with an optimum duration of 183 days

Downloads

Published

2024-10-16

How to Cite

Aziz Irsyad, Ika Arum Puspita, & Wawan Tripiawan. (2024). Schedule Acceleration Planning in Construction Project (Case Study: Japek II Selatan Tollroad). International Journal of Innovation in Enterprise System, 6(1), 24–37. https://doi.org/10.25124/ijies.v6i01.145

Citation Check

Similar Articles

1 2 > >> 

You may also start an advanced similarity search for this article.